We Got FAC of Baghabari & Daudkandi Power Plant
We got Final Acceptance Certificate (FAC) of Baghabari 50MW Power Plant and Daudkandi 50MW Power Plant on November 4th, 2013, based on the successful completion of defect liability period and running well of last two years.
Baghabari 50MW Power Plant was completed on September 20th, 2011 and Daudkandi 50MW Power Plant was completed on October 19th, 2011. As per requirement of EPC Contract, we should take responsibility of defect liability and running for two years after commissioning of the power plant. The employer was satisfied and gave high regards for our running work during the last two years.