Successful Installation of Mainframe at Baghabari 50MW Power Plant
6 mainframes of Baghabari 50MW power plant were successfully installed by the building contractor CCC Engineering Limited on May 10th. This great periodical success definitely settled the firm basis for the whole incorporation electricity generation project which will comprehensively start at the end of August.
Withstanding the high temperature during the daytime and the mosquito biting at night and even lacking of the large lifting equipment, the technical personnel fearing neither hardship nor tired transported the 6 mainframes from wharf to the construction site and installed them smoothly after 3 day’s hard-working. The whole procedure impressed the Bangladeshi supervisors deeply considering its systematic arrangement and smoothness.
The installation of the mainframe has been settling a good foundation for the next coming module adjustment, installation of exhaust system, fuel piping system and compressed air system.