Pakistan's 132 kV Substation and Transmission Line Project Signing Ceremony

On November07, 2014, under the witness of Counsellor Mr.Yan Jianming and Secretary Mr. Zhang Rui from Economic &Commercial Office of China Embassy, CCCE and HESCO held the contract signing ceremony of the project: Three (3) Nos. conversions from 66KV to 132KV (AIS) Grid Stations along with allied Transmission Line on turnkey Basis.
CCCE was awarded the project after ahalf-year evaluation process. The project funds are wholly owned loans of Asia Development Bank (ADB).